Multipurpose Room lighting
August 12 2005. Photos by Thieu
The Newly Renovated Kensington Hilltop School opened for school August 23, 2005
Construction updates link: www.wccusdbondprogram.com/sb_reports/construct_reports.asp
Ceiling. August 12 2005. Photos by Thieu
Front of School Parking. August 12 2005, Photos by Thieu New Library. August 12 2005, Photos by Thieu
New perimeter fence. August 12 2005, Photos by Thieu New retaining wall, east side of campus. August 12 2005, Photos by Thieu

___________________________________________________
Letter from Lewis Brower, WCCUSD • August 24. 2005

To All,

Progress Meeting #61 was undertaken on an informal basis so as not to take time and focus off the first day of the new school year and first day of operations at the new school. While Gary could not attend and Romer was committed at Harding, Les was at Kensington along with Frank, Thieu and Lew.

Essentially, the meeting was very informal and primarily provided an opportunity for Les, Frank and Lew to address various issues. Les will also visit Kensington on Thursday morning to meet with Frank and Lew, and hold a phone conference with Gary. 

No formal Minutes will be issued this week; an overview of Project Status is as follows:

1.   Asphalt surface was placed for the Staff Parking lot (the east side of Building A3 possibly Friday, most likely Saturday) to include the partial frontage at the walkway of the New Building (north of A3, and wrapping around to the canopy walkway between A3 & A4). Stripping will  is scheduled to accomplished  on Saturday, 8/27/05. 

2.    Also accomplished over this past weekend:

a.     A seal coat was applied on the Kindergarten playground and the area between Buildings A2 & A3
  b.    A tack coat and asphalt overlay was applied to the Library Access Road
  c.    Installation of the remaining various handrails and windscreens commenced
  d.    The exteriors of the Child Care Modular Units were painted
  e.    Various electrical issues were addressed

3.    On-going work over this week:

  a.    Handrail/windscreen installation will continue for several more days
  b.    The 1st and 2nd floor lobbies and stairwell of the new building is now receiving the finish stucco coat - this work should be complete Thursday.
  c.    Painting of the canopies between Buildings A3 & A4 is underway and the Painters will move on to the remaining handrails and windscreens as well as the new building lobbies
  d.    The Electricians should complete troubleshooting of the Public Address system and it should be in service today. They maintain a full time presence as they address some remaining issues and punchlist work
  e.    Carpenters & Laborers are maintaining a full time presence to perform site clean-up/debris removal and punchlist work.
  f.    A Landscape crew is installing the plantings and start-up of the irrigation system - this will continue over the next couple of weeks
  g.    The playground structure, benches and athletic equipment will be installed as items are received.
  h.    All Kitchen Equipment has not as yet been received - cold pack sandwich meals are being held and dispensed through the equipment now installed

4.     Reasonable expectation is that all remaining construction contract work, including most change order work, will be completed around the middle of September. This includes the new building lobbies/elevator, all playgrounds, landscaping, irrigation and exterior improvements. We anticipate most finish punchlist work will also be complete by mid September; however, punchlist inspections by the Electrical, Mechanical and Civil Engineering Consultants still need to be performed.

5. SBC continues installation and troubleshooting to establish telephone and computer services.

Lew


Link to: July 5 2005 • Construction Meeting Notes

First layer of stucco. August 12 2005. Photos by Thieu
New Building July 2005
Kensington Hilltop School Playstructure
Memorabilia
Available

• • • • • • •

WCCUSD is excited about the future remodeling of Kensington Elementary School.
Construction will begin in 2004 and will last about a year.

  • A new two-story wing will be added to the west end of the school and will contain four classrooms,a library/media center,a science/art center,and restrooms.
  • The administration area will be redesigned to meet current and future needs.
  • The multi-purpose room and kitchen will be modernized and remodeled.
  • Existing classrooms will receive new paint,windows,heating/electrical/plumbing systems,and cabling for computers.
  • The parking lot will be reconfigured to improve circulation and safety

If you want to talk with someone about the project,
please call Tony Catrino, Bond Program Manager, at (510) 412-5657.